MRT Line 2, Titiwangsa Underground Station, Kuala Lumpur

RC works for underground station at MRT Line 2 Titiwangsa Station.
2017 - 2021
In partnership with Shanghai Tunnel E&C, we undertook RC scope of works for the station underground structure, entrance A & B, internal lining walls, infill slabs and raft foundation.

Key Facts



Main Contractor - MMC-Gamuda KVMRT (T) Sdn Bhd
Work Package Contractor - Shanghai Tunnel E&C (M) Sdn Bhd
RC Sub-Contractor - SEAL Consult Sdn Bhd
System Form - PERI Duo System & SB Brace Frame (Wall), PERI PD8 Shoring (Slab)